- Country
- Romania
- Location
- Bacau
- Area
- 13,500 m²
- Service
- Industrial Concrete Flooring
- Floor type
- Superflat FM2
- Year
- 2025
The ARENA City Center project in Bacau required a high-performance industrial flooring solution for a massive 13,500 m² retail and distribution hub. The primary challenge was the scale of the facility combined with the stringent requirements for surface regularity. As a high-traffic environment, the client required a floor that could withstand heavy mechanical loads while maintaining an aesthetic finish suitable for a modern commercial center.
Furthermore, the project timeline was compressed, requiring a logistical strategy that could handle large-volume concrete pours without compromising on the precise tolerances required for FM2 classification. Any deviation in flatness would not only affect the operation of material handling equipment but also the long-term durability of the slab under constant use.